Public Safety Center | October 2018 Update – Utilities Completed

During the month of October 2018, Alten Construction finished with the slab on grade at the basement level and all of the offsite utilities (water, sewer, storm drain and gas). The contractor then proceeded with the installation of the shoring for the first floor (podium deck). All of the contractor’s forces have been focusing on … Continued

Public Safety Center | August 2018 Update – Installation of Underslab Utilities

Project Progress During the month of August 2018, Alten Construction continued with the forming of the shotcrete walls for the remaining perimeter of the basement along Via Sessi and interior walls. Contractor also continued with the installation of underslab utilities Storm Drain, Sewer, Drainage Systems, waterproofing, water stoppers, electrical conduits and electrical boxes, rebar and … Continued

Public Safety Center | July 2018 Update – Shotcrete Walls

During the month of July, Alten Construction continued with the forming of the shotcrete forms (walls) for the remaining perimeter of the basement including the apparatus bay. Major coordination of the shotcrete walls took place, setting doors, waterproofing, water stoppers, electrical conduits and electrical boxes, rebar, dowel templates MEP penetrations and screed wire. Once completion of the shotcrete forms … Continued

Public Safety Center | June 2018 Update – Rebar Installation Completed

During the month of June, Alten Construction completed the excavation of all footings and spread footings. Rebar installation for strip and spread footings were completed, inspected, and poured in place. Contractor also erected, formed and poured all basement columns. The installation of the shotcrete forms began by erecting all the forms along C-Street and 5th … Continued

Public Safety Center | May 2018 Update – First Concrete Pour

Project Progress During the month of May, Alten Construction continued with the excavation of footings, elevator pits / stairs, and underground utilities (storm drain, fire line, sewer, waterlines, electrical and any sleeves required for future plumbing). After review /acceptance of the footing excavations by the geotechnical engineer, the contractor installed all the conduits and rebar … Continued

Public Safety Center | April 2018 Update – Clean Material Hauloff

During the month of April 2018, the weather cleared up allowing Alten to initiate the off haul of the clean material, contaminated material and prepare the building pads for certification. Hauling off of the clean material was a success hauling off approximately 2,500 cubic yards to the airport. During the excavation of the contaminated material … Continued

Public Safety Center | March 2018 Update – Pumping Rain Water

During the month of March, the weather turned for the worst raining constantly pushing the site to its limits forcing the team to act quickly. An additional baker tanks was brought to the site and the purchase of pumps was required to help contain the rain water on site. The pumps had to be placed … Continued

Public Safety Center Update February 2018 – Notice to Proceed Cleared

Great news! The Public Safety Center notice to proceed will be issued next Monday, February 5.  The site is completely cleared, the office trailers have been dropped off, and the contractor’s A team is ready to go.  The pre-construction meeting took place this week where Police and Fire Chiefs expressed their excitement for this new … Continued