Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

Public Safety Center | July 2018 Update – Shotcrete Walls

Posted on August 27, 2018


public safety center update July 2018

During the month of July, Alten Construction continued with the forming of the shotcrete forms (walls) for the remaining perimeter of the basement including the apparatus bay. Major coordination of the shotcrete walls took place, setting doors, waterproofing, water stoppers, electrical conduits and electrical boxes, rebar, dowel templates MEP penetrations and screed wire. Once completion of the shotcrete forms (walls) contractor set up scaffolding for shooting of the shotcrete. The IOR, City inspector and the Structural Engineer all have been to the sit performing random inspection assuring proper installations. In addition review and processing of submittals and Request for Information (RFI’s) continue in high volume/pace.

PROJECT TEAM

Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor: Alten Construction, Inc.

Download the full update here!

Back to Monthly Updates

Close window