2019 Sidewalk Repair Program Update

The City of San Rafael will be accepting applications for the 2019 Sidewalk Repair Program beginning Tuesday April 2nd through Friday, May 17th. This will mark the second year of the City’s program aimed at assisting property owners with sidewalk, curb, and gutter repair. Residential property owners accepted into the program split the cost of sidewalk replacement (50-50) … Continued

Public Safety Center | October 2018 Update – Utilities Completed

During the month of October 2018, Alten Construction finished with the slab on grade at the basement level and all of the offsite utilities (water, sewer, storm drain and gas). The contractor then proceeded with the installation of the shoring for the first floor (podium deck). All of the contractor’s forces have been focusing on … Continued

Fire Station 57 Update September 2018

Project Progress During the month of September, Alten Construction substantially completed high roof steel erection and 1st Floor electrical and plumbing rough-in. High roof decking over the Apparatus Bay was started and completed. Work began on mechanical rough-in and framing for the 1st Floor, site-specific storm-drain, and Storage Building construction. PROJECT TEAM: Owner: City of San Rafael Project/Construction Manager: … Continued

Fire Station 57 September 2018 Update

Project Progress During the month of September, Alten Construction substantially completed high roof steel erection and 1st Floor electrical and plumbing rough-in. High roof decking over the Apparatus Bay was started and completed. Work began on mechanical rough-in and framing for the 1st Floor, site-specific storm-drain, and Storage Building construction. PROJECT TEAM: Owner: City of San Rafael Project/Construction Manager: … Continued

Fire Station 57 Update August 2018

Project Update: The Public Safety Center team continues with concrete placement.  The interior shotcrete walls are almost complete in the basement.  The soils that were stockpiled on the north west corner of the site is completely gone as the contractor prepares for their first slab on grade installation in the next couple of weeks. Site … Continued

Fire Station 52 Update August 2018

Project Update:  The construction team continues to show evident results at our Essential Facilities projects. At Fire Station #52, with the training tower complete, the contractor has refocused its resources to interior build out of the main building, exterior façade, on-site, and off-site utilities activities.    Bay Cities Paving & Grading, a subcontractor to Alten, will … Continued

Public Safety Center | August 2018 Update – Installation of Underslab Utilities

Project Progress During the month of August 2018, Alten Construction continued with the forming of the shotcrete walls for the remaining perimeter of the basement along Via Sessi and interior walls. Contractor also continued with the installation of underslab utilities Storm Drain, Sewer, Drainage Systems, waterproofing, water stoppers, electrical conduits and electrical boxes, rebar and … Continued

9/4/18 – Sidewalk Repair Program Update

Public Works and contractors have been hard at work answering sidewalk repair inquiries and final inspection scheduling all throughout late July and August. Thank you to all applicants that have arranged for the final inspection required with their preferred contractor before the deadline. Do not be alarmed if contractors are slow to respond, doubling of … Continued

Fire Station 57 Update July 2018

Project Update:  At Fire Station #57, the contractor has completed most of the concrete masonry block walls for the Fire Station building.  The structural steel was delivered at the end of July and the contractor quickly mobilized an erection crew and got the steel installed in only four days.  Steel erection for the second floor … Continued