Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

Category: Fire Station 52

Grand Opening Celebration of Fire Station 52

Join us next Monday, May 13 at 5 p.m. for the Hose Uncoupling Ceremony and Housing of the Engine at the grand opening of Fire Station 52! Refreshments will be served and tours of the new station will be conducted. We hope to see you there!

Fire Station 52 – Project completion is approaching

The Contractor has been working in the rain and on the weekends to complete our new Fire Station 52.  They are installing interior finishes and completing testing and commissioning of equipment.  They will be pouring the last portion of the approach, curb, and sidewalk by the end of next week.  Pavers, side gates and planting … Continued

Fire Station 52 Update August 2018

Project Update:  The construction team continues to show evident results at our Essential Facilities projects. At Fire Station #52, with the training tower complete, the contractor has refocused its resources to interior build out of the main building, exterior façade, on-site, and off-site utilities activities.    Bay Cities Paving & Grading, a subcontractor to Alten, will … Continued

Fire Station 52 Update July 2018

Project Update: During the month of July, Alten Construction continued MEP rough-in and framing at the Main Building. Fire  roofing was completed. Exterior roofing/sheathing commenced. Drywall tape/finish occurred at the Classroom, as well as TPO roofing. The concrete decking for the Training Tower was completed while finishes commenced. Work began for the on-site/off-site utilities and storm drain. PROJECT … Continued

Fire Station 52 Update June 2018

Project Progress During the month of June, Alten Construction completed MEP and fire protection rough- in at the Fire Station building. Framing activity continued on the 1st and 2nd floors as well. At the Classroom building, insulation, drywall and exterior plater were completed. TPO roofing and flashing were substantially completed as well. Site CMU was completed … Continued

Fire Station 52 Update May 2018

Project Progress During the month of May, Alten Construction work progressed on the Fire Station Building, the Training Classroom and the Training Tower. The Tower erection began the first of May and neared the structure 50’ top out at the end of the period. The Classroom stucco system brown coat was applied and completed the … Continued

5/15/18 – Fire Station 52 Update April 2018

Project Update During the month of April, Alten Construction continued work on the Fire Station Building, the Training Classroom and the Training Tower. The Training Tower foundation slab on grade was placed mid-April. The Tower structure design submittal was approved and in early May the Tower erectors will be on site to begin erection. The … Continued

4/25/18 – Fire Station 52 Update March 2018

Project Update: During the month of March, Alten Construction continued work on the Fire Station Building and the Training Classroom. The Training Tower foundation work initiated with anchor pier delivery, installation and successful pull-testing. Tower footing rebar installation was ongoing at the end of the period. At the Fire Station Building, the CMU block was … Continued

Fire Station 52 Update February 2018

Project Progress Alten Construction continues to work on the Fire Station and Classroom Buildings.  At the Fire Station Building, the CMU walls are going up along with electrical and plumbing rough in work.  At the Classroom Building, the Contractor continues their wood framing and electrical rough in.  The Contractor also completed the concrete work for … Continued

Fire Station 52 Update January 2018

Project Update: During the month of January, Alten Construction continued to work on the Fire Station Building; the Classroom Building and the retaining wall/ bio-retention on the North-East side of the site. At the Fire Station Building, contractor continued with installation of Scaffolding, wood framing at the bay room and the CMU Block. The CMU … Continued

Close window