We need your input! Please take a moment to fill out our website satisfaction survey by clicking here.

Fire Station 52 Update June 2018

Posted on July 16, 2018


Fire Station 52 June Updates

Project Progress

During the month of June, Alten Construction completed MEP and fire protection rough- in at the Fire Station building. Framing activity continued on the 1st and 2nd floors as well. At the Classroom building, insulation, drywall and exterior plater were completed. TPO roofing and flashing were substantially completed as well. Site CMU was completed as was erection of the Training Tower.

PROJECT TEAM:
Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor – Alten Construction, Inc.

Download the full update here!

Back to Monthly Updates

Close window