Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

Author: nallely.manriques@cityofsanrafael.org

Fire Station 52 Update July 2018

Project Update: During the month of July, Alten Construction continued MEP rough-in and framing at the Main Building. Fire  roofing was completed. Exterior roofing/sheathing commenced. Drywall tape/finish occurred at the Classroom, as well as TPO roofing. The concrete decking for the Training Tower was completed while finishes commenced. Work began for the on-site/off-site utilities and storm drain. PROJECT … Continued

Public Safety Center | July 2018 Update – Shotcrete Walls

During the month of July, Alten Construction continued with the forming of the shotcrete forms (walls) for the remaining perimeter of the basement including the apparatus bay. Major coordination of the shotcrete walls took place, setting doors, waterproofing, water stoppers, electrical conduits and electrical boxes, rebar, dowel templates MEP penetrations and screed wire. Once completion of the shotcrete forms … Continued

Public Safety Center | June 2018 Update – Rebar Installation Completed

During the month of June, Alten Construction completed the excavation of all footings and spread footings. Rebar installation for strip and spread footings were completed, inspected, and poured in place. Contractor also erected, formed and poured all basement columns. The installation of the shotcrete forms began by erecting all the forms along C-Street and 5th … Continued

Fire Station 52 Update June 2018

Project Progress During the month of June, Alten Construction completed MEP and fire protection rough- in at the Fire Station building. Framing activity continued on the 1st and 2nd floors as well. At the Classroom building, insulation, drywall and exterior plater were completed. TPO roofing and flashing were substantially completed as well. Site CMU was completed … Continued

Fire Station 57 Update June 2018

Project Progress During the month of June, Alten Construction completed the CMU installation for the Apparatus Bay. Steel elements (in conjunction with CMU activities) were completed for the Living Quarters. Embedded MEP elements were completed and the concrete slab was poured for the Apparatus Bay and Living Quarters. Shop fabrication for remaining steel commenced. Potholing … Continued

Fire Station 52 Update May 2018

Project Progress During the month of May, Alten Construction work progressed on the Fire Station Building, the Training Classroom and the Training Tower. The Tower erection began the first of May and neared the structure 50’ top out at the end of the period. The Classroom stucco system brown coat was applied and completed the … Continued

Fire Station 57 Update May 2018

Project Progress During the month of May, Alten Construction completed the slab on grade for the Office and Living Quarters areas. CMU installation for the Utility Rooms was completed and continued for the Apparatus Bay and Living Quarters. The installation of steel elements (ledgers and columns) continued for the Living Quarters. Installation of supports for … Continued

Public Safety Center | May 2018 Update – First Concrete Pour

Project Progress During the month of May, Alten Construction continued with the excavation of footings, elevator pits / stairs, and underground utilities (storm drain, fire line, sewer, waterlines, electrical and any sleeves required for future plumbing). After review /acceptance of the footing excavations by the geotechnical engineer, the contractor installed all the conduits and rebar … Continued

5/15/18 – Fire Station 57 Update April 2018

Project Update During the month of April, Alten Construction completed the installation of under-slab rough electrical and plumbing elements, and also completed the placement of underslab rock and vapor barrier at the Living Quarters. CMU installation continued at the Apparatus Bay and Utility Rooms. Selected steel elements (ledgers and columns) and steel door frames were … Continued

Close window