We need your input! Please take a moment to fill out our website satisfaction survey by clicking here.

Fire Station 57 September 2018 Update

Posted on November 9, 2018


Fire Station 57 Update September 2018

Project Progress

During the month of September, Alten Construction substantially completed high roof steel erection and 1st Floor electrical and plumbing rough-in. High roof decking over the Apparatus Bay was started and completed. Work began on mechanical rough-in and framing for the 1st Floor, site-specific storm-drain, and Storage Building construction.

PROJECT TEAM:
Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor – Alten Construction, Inc.

Download the full report here!

Back to Monthly Updates

Close window