2020 Sewer Replacement Phase 2 – Weekly Update June 30th

Project Update The contractor replaced sewer main and sewer laterals and temporarily paved on Jordan St  and Locust St The contractor is replacing sewer main and sewer laterals on El Camino Drive from June 22th to June 30th The contractor replaces sewer main and sewer laterals on Ivy Lane and Marten Blvd  from July 3rd to … Continued

2020 Sewer Replacement Phase 2 – Weekly Update May 22nd

Project Update Replaced sewer main and sewer laterals and temporarily paved the road on 1st St and C St The contractor replaces sewer main and sewer laterals on Tayler St and C St from May 18th to June 2nd. The contractor will replace sewer main and sewer laterals on Elford St and Willow St from … Continued

2020 Sewer Replacement Phase 2 – Weekly Update May 5th

Project Update The contractor replaces sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th. The contractor will replace sewer main and sewer laterals on 2nd St and E St from May 22th to June 6th.

2020 Sewer Replacement Phase 2 – Weekly Update April 26th

Project Update Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Clayton St The contractor will replace sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th. The contractor will replace sewer main and sewer laterals on 2nd St and East St … Continued

2020 Sewer Replacement Phase 2 – Weekly Update April 10th

Project Update Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Welch St Replaced sewer main on Clayton St from Marin St to Welch St The contractor will replace sewer main and sewer laterals on Clayton St from April 10th to April 21th.

2020 Sewer Replacement Phase 2 – Weekly Update March 27

Project Update – Week of 3/27 Replaced sanitary sewer mains and laterals on  on 1st St from Shaver St to Welch St.  Replaced sanitary sewer mains and laterals on  Welch St and on 1st St from Clayton St to 1st St.  Sewer Main replacement on Clayton St from Welch St  is between 4/6  to 4/21.  … Continued

2020 Sewer Replacement Phase 2 – Weekly Update February 21th

Project Update – Week of 2/20 WR Forde completed sanitary sewer main replacement on Marin St from Clayton Ave to Ross St. Sewer laterals on Marin from Clayton Ave to Ross St will be replaced and expected to be completed by February 24th. From 2/20 – 3/10, WR Forde will be on Clayton Ave and … Continued

Bayside Acres Phase B – Weekly Update February 9th

Project Update – Week of 2/9 WR Forde will be onsite Saturday 2/11 to CCTV the newly installed laterals completed late last year. This won’t impact traffic traveling through the area or any residents as the laterals were completed within the city and county right of way. In addition, the design team Nute Engineering has … Continued

Bayside Acres Phase A – Weekly Update December 5th

Project Update – Week of 12/05 WR Forde will be repaving the street along Point San Pedro and Main Dr. starting Thursday 12/8 until Friday 12/9. The eastbound section of PSP will be closed and traffic rerouted to the westbound road creating a single lane in either direction. All traffic should be prepared to slow … Continued