Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

2020 Sewer Replacement Phase 2 – Weekly Update May 22nd

Posted on May 22, 2023


Project Update

Replaced sewer main and sewer laterals and temporarily paved the road on 1st St and C St

The contractor replaces sewer main and sewer laterals on Tayler St and C St from May 18th to June 2nd.

The contractor will replace sewer main and sewer laterals on Elford St and Willow St from May 24th to June 16th.

The contractor replaces sewer main and sewer laterals on 5th Ave and Hart St from May 22th to June 9th.

 