Bayside Acres Beach Sewer Relocation Project – Phase B1- Update

As of July 10th, 2024, Phase B1 is 95% complete. The properties that were previously connected to the corroded and inaccessible sewer mainline along the shore, were successfully connected to the sewer mainline on Oak Drive. Each property had an individual sewer pump system, and lateral  installed on their property in order to connect to … Continued

Miramar/Miraflores – Update

Project Update Replaced sewer main and lower laterals on Miramar Ave starting at the intersection of 1st Street and Miramar Ave to approximately 450 feet uphill on Miramar Ave. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. The contractor is installing sewer main on Miramar Avenue between intersections … Continued

2023 Sewer Pipe Burst – Update November 1

Project Update Replaced sewer main and lower laterals on Highland Ave starting at Jewell Street to approximately 400 feet east up Highland Ave. Replaced sewer main and lower sewer laterals on Spring Grove Ave between Greenfield Avenue and Terrace Avenue from September 30th to October 20th. Replacing sewer main and installing cleanout and backflow prevention … Continued

2023 Sewer Pipe Burst – Update October 9

Project Update Replacing sewer main and lower sewer laterals on Highland Ave starting at Jewell Street to approximately 400 ft East up Highland Avenue from September 30th to October 20th. Replacing sewer main and lower sewer laterals on Spring Grove Avenue between Greenfield Avenue and Terrace Avenue from September 30th to October 20th. Replacing sewer … Continued

2023 Sewer Pipe Burst – Update September 28

Project Update Replacing sewer main and lower sewer laterals on Alexander Ave starting from W Crescent Dr including 78 to 40 Alexander Ave and the sewer pipes in sewer easement from 16 Alexander to 7 Alexander Ave from September 21st to October 6th. Replacing sewer main and lower sewer laterals on Glen Park Ave near … Continued

2020 Sewer Replacement Phase 2 – Weekly Update August 22

Project Update Replaced sewer main and sewer laterals on Woodland Ave, Irwin St, and Duffy Pl The contractor replaces sewer main and sewer laterals on Locust Ave from August 7 to September 1st. The contractor replaces sewer main and lower laterals on Ivy Ln from August 22 to September 1st.

2020 Sewer Replacement Phase 2 – Weekly Update July 14th

Project Update Replaced sewer main and sewer laterals on Elford St, Willow St, Jordan, and Locust St. The contractor replaces sewer main and sewer laterals on Lincoln St, Irwin St, and Duffy Street from July 10th to August 11th. The contractor will restore paving on El Camino Ave from July 17th to July 18- and … Continued