Updates to City Hall Hours on Fridays in July and August 

 

Category: East San Rafael Parking

Spinnaker Point parking modification

JC Agcaoili, Assistant Engineer Final paving and concrete work is now complete on the Department of Public Works’ Spinnaker Point Parking Modification project.  The remaining operations for the project will be the planting and striping of the new parking spaces.  The current forecast is still showing some rain which will impact the days during which … Continued

Windward Secure After-Hours Parking Pilot Program

The Canal Area Parking Taskforce recommended the consideration of Windward Way to provide secure on-street and overnight parking. The City team made significant progress in designing a visual concept and further explanations of how that concept would function to achieve the ultimate goals. The implementation of this idea would require a significant initial investment by … Continued

Spinnaker Point and Baypoint Village Parking Modifications

The evaluation of the T’s and L’s parking markers for both Spinnaker Point and Baypoint Village roadways have been completed. The objective is to maximize the number of vehicle parking spaces with the installation of T’s and L’s pavement markings. This approach would add a net gain of 41 additional parking spaces. The work will … Continued

Spinnaker Point parking modification

Construction is almost complete on the Department of Public Works’ Spinnaker Point Parking Modification Project.  Our contractor, Michael Paul Co., expects all major construction operations, such as concrete and asphalt, to be complete within the next two weeks.  The current forecast shows some rain and cold temperatures ahead.  Due to this weather forecast, we have … Continued

Spinnaker Point parking modification

Construction is almost complete on the Department of Public Works’ Spinnaker Point Parking Modification project.  Our contractor, Michael Paul Co., expects all major construction operations such as concrete and asphalt to be complete within the next two weeks.  The current forecast shows some rain and cold temperatures ahead.  Due to this weather forecast, we have … Continued

Spinnaker Point Parking Modification

Construction for the Spinnaker Point Park Modification project began on Monday, October 10th. The initial construction stages of the project include demolition of the existing sidewalk and grading of the adjacent landscape. Environmental measures have been put in place to protect the local wildlife in accordance with environmental regulatory permits. The project has a projected … Continued

Canal Neighborhood Parking Study

One of the big transportation issues in the Canal neighborhood is the on-street parking supply that can’t keep up with the parking demand. With the help of W-trans, and in collaboration with Parking Services, the area has been studied and assessed for potential improvements. After changing the parking time limits to 24 hours in the … Continued

Canal neighborhood parking study

One of the big transportation issues in the Canal neighborhood is the on-street parking supply that can’t keep up with the parking demand. With the help of W-trans, and in collaboration with Parking Services, the area has been studied and assessed for potential improvements. After changing the parking time limits and getting the ability to … Continued

Close window