Francisco Blvd East Project completed – Vivian to Medway

Posted on November 6, 2020


The City’s contractor on Francisco Blvd East has made significant progress over the past several weeks by completing the installation of storm drainpipe between Vivian and Harbor Streets. The new sidewalk has been installed in multiple stretches, including Vivian to Medway and Hoag to Harbor. The contractor’s electrician has installed foundations and underground conduit for the new street lighting system as well. With this progress, the contractor is preparing to move into the next block from Harbor to Bay St. The City’s on-site construction inspector will soon go door-to-door to provide advance notification to businesses and tenants of the pending work. The contractor remains on schedule to complete the project in Spring 2021.