We need your input! Please take a moment to fill out our website satisfaction survey by clicking here.

Fire Station 57 Update February 2018

Posted on March 26, 2018


Fire Station 57 construction update February 2018

Project Update

The team has made excellent progress at Fire Station #57. During the month of January, the new driveway and side walk were completed along Civic Center Drive. The foundation formwork and rebar are underway as well as the elevator pit concrete work.  We are excited to see this project moving at full speed.

PROJECT TEAM:
Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor – Alten Construction, Inc

Download full update here!

Back to Monthly Updates

Close window