The City Hall building will be closed to the general public on Fridays from June 6, 2025 through August 29, 2025. San Rafael Community Centers, Libraries, Al Boro Parking Services, and all Public Safety services will remain open and maintain normal Friday hours.
The Bayside Acres Beach Sewer Relocation Project – Phase B2 began on February 25th. The installation of five residential pump systems, and site restorations took place within a two month period. As of August 2025, the project is 90% complete. The Contractor is working with the District and PG&E to ensure a residential electrical system … Continued
The Bayside Acres Beach Sewer Relocation Project – Phase B1 was successfully completed on September 18th, 2024. A Notice of Completion was filed with the County of Marin on October 30th, 2024, and recorded on November 5, 2024. For further information about the project, please contact, Cindy Diaz, Project Engineer, via email at cindy.diaz@cityofsanrafael.org.
Project Update 07/14/2025 SRSD replaced the sewer mainline and installing a wet well and valve pit for a new pump station in 3rd Street in front of the San Rafael High School.
Project Update 07/14/2025 SRSD is replacing the sewer mainline at 1595 Francisco Blvd East from July 5th- August 8th, including restoration of the ground surface upon completion.
Project Update 01/13/2025 SRSD will be replacing the sewer mainline and lower laterals on 5th Avenue from January 13th- 17th. The construction crew will working from Nye Street to 918 5th Avenue. SRSD will be replacing the sewer mainline and lower laterals on Clyde and Belle Ave from January 20th, 2025 to January 24, 2025. … Continued
As of January 10th, the following locations have been completed: Madrona Street Billou Street Edgewood Way McCoy Road, 4th St and C St. Bayo Vista Way Terradillo Easement between Marinita Ave and Terradillo Ave. 4th St. between Mary St and Grand Ave. The following work is scheduled to take place over the next month: West … Continued
As of October 14th, 2024, Bayo Vista Way and Terradillo Ave Easement have been completed. The following work is taking place on the following streets: Billou St.: The remaining lateral reconnections will be completed by October 25th, and paving will take place the last week of October. Madrona St: The sewer mainline installation and lateral … Continued
Project Update 8/21/24 The contractor plans to pothole and video existing sewer pipes on August 26th Replaced all seer main and lower laterals Grind and repave road on Miramar Ave and Miraflores Ave The contractor will abandon existing sewer main
Project Update 7/30/24 Replaced sewer main and lower laterals from 26 Miramar Ave uphill to Miraflores Avenue approximately 500 feet from 7/10-7/30/24. Installed new sewer main and extending existing sewer laterals on the eight feet lane easement. Installed new sewer manholes on Miramar Ave.