THIS WEEK (August 8 – 12):

  • Nightwork for water service connections completed on Third Street between San Rafael High School and Irwin Street.
  • Installed street light conduits and excavated for light pole foundations at Third Street and A Street.
  • Continued the sanitary sewer replacement by open trench method in the westbound lanes of Second Street from Ida Street to Fourth Street.
  • Crews reset utility boxes in preparation for sidewalk replacement between East Street and West Street for ADA improvements.
  • Crews erected form panels for the retaining wall on Second Street between East Street and Miramar Avenue.
  • PG&E continued undergrounding utility poles in the blocks of Marquard Avenue and G Street.
  • Drilling crews mobilized and prepared the drill soil anchors for retaining wall.

NEXT WEEK (August 15 – 19):

  • Continue the installation of conduit and the excavation of light pole foundations at the intersection of Third Street and Brooks Street.
  • Sanitary sewer rehabilitation: crews will continue installing new sewer pipe and laterals by open trench method in the westbound lanes of Second Street from Ida Street to Fourth Street.
  • Crews will demolish median island separating Ida Street and Second Street at G Street.
  • Pouring of new concrete curb ramps and sidewalks on Second Street between East Street and West Street.
  • Begin trenching and installing new water main on Third Street between Irwin Street and Hetherton Street.
  • Crews will drill soil anchors for the new retaining wall.
  • MMWD will relocate fire hydrants on Second Street between East Street and West Street.

08.11.22 Photo 4

IMPACTS:

  • Beginning August 1, 2022, PG&E will start its electrical relocation project on Second Street from Fourth Street to Miramar Avenue.
  • The stairway from Second Street to Jessup Street (south of Ida Street) is currently closed.
  • For the Lane Shift on Second Street the posted speed limit is 25 mph, drivers should be aware of changed conditions and be alert.
  • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
  • Curb parking spaces will be marked “No Parking.”

For more information, visit the project website or contact the City at thirdstreet@cityofsanrafael.org.

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.