Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

Watch the City Council meeting on YouTube at 6:00 p.m.

Third Street Improvement project – 2/18/22 weekly update

Posted on February 18, 2022


Third street - project limits

The City of San Rafael will be sending out weekly project updates with construction updates, traffic closure updates, and other relevant information for this project. To receive these updates, please sign up using the form at the left-hand side of the project website.


On Monday, February 7, 2022, the San Rafael City Council awarded the Third Street Rehabilitation construction contract to Ghilotti Brothers. Construction is anticipated to begin in late February 2022 and last around 18 months.

NEXT WEEK (February 21-25): The contractor will start potholing to identify the location of utilities and identify potential conflicts.

IMPACTS: Expect lane closures and road work eastbound on Second Street between 9 am and 6 pm and west bound on Third and Second Streets from 6 am to 3 pm.

Thank you for all of your input during the design stage and we look forward to the construction process.

For more information, visit the project website or contact the City at thirdstreet@cityofsanrafael.org.

Please note: all estimated timelines are tentative and subject to change.

Close window