THIS WEEK (March 6 – March 10):

  • Due to heavy rainfall, no work was planned for Thursday or Friday
  • Contractor crews replaced the sanitary sewer lateral on 3rd Street from Lootens Place to A Street.
  • Crews placed concrete for curb ramps at the northwest corner of Third Street and A Street.
  • Crews placed concrete for curb ramps at the northwest corner of Second Street and G Street.
  • Crews removed asphalt pavement for the construction of the new median islands on Second Street from Marquard Avenue to G Street.
  • Crews potholed to locate storm drains at Second Street and G Street, and Third Street and B Street.
  • Crews replaced a section of sidewalk at 1654 Second Street.
  • Crews shifted traffic lanes to the south on Second Street between Marquard Avenue and Shaver Street.

NEXT WEEK (March 13 – March 17):

  • Crews will continue replacing a section of sidewalk at 1654 Second Street. This work will require a lane closure and no parking on westbound Second Street.  
  • Crews will place concrete for curb ramps at the northwest corners of Third Street and C Street, and Third Street and B Street. This work will require curb lane closure and no parking adjacent to the intersections. 
  • Crews will replace storm drains at Second Street and G Street, and Third Street and B Street. This work will require curb lane closure and no parking adjacent to the intersections.
  • Crews will begin to construct the new median islands on Second Street from West Street to G Street. The work will require a lane closure and traffic lane shift. 
  • Crews will install and raise sidewalk pull boxes along Third Street. This work will require a curb lane closure during the installation of the pull boxes. 
  • Crews will replace the sanitary sewer lateral main on Third Street between A Street and Lootens Place. This work will require a lane closure on Third Street. 
  • Crews will replace the sanitary sewer lateral main on Third Street between Lincoln Avenue and Cijos Street. This work will require a lane closure on 3rd St. 

 IMPACTS:

  • The stairway from Second Street to Jessup Street (south of Ida Street) is closed.
  • For the lane shift on Second Street, the posted speed limit is 25 mph. Drivers should be aware of changed conditions and be alert.
  • Traffic Controls (temporary signs, message boards, traffic cones, delineators and detour signs) will be put in place to direct motorists through the work area.
  • Curb parking spaces will be marked “No Parking.”

The hours of work will be 6:00am – 6:00pm and lane closures 6:00am – 3:00pm on Third Street and Second Street westbound, and 9:00am – 6:00pm on Second Street eastbound.