Public Safety Center Construction Update – December 2019

Posted on December 6, 2019


Progress photo – view from City Hall

Construction of the Public Safety Center continues to move forward despite the weather conditions. In fact, the rainfall gave the contractor’s team the opportunity to test the building’s waterproofing. The facility’s basement is completely built, and its walls are painted. Additionally, rollup doors have been installed. Currently, the first-floor is being painted. The exterior stucco on Via Sessi and some of the south elevation is pretty much complete. The brick veneer will be delivered next week for the contractor to start installation. More information