All City facilities are currently closed for walk-in service. Please call to find out more details about the services you are interested in.

COVID-19 (novel coronavirus) information and resources

Watch/participate in the City Council meeting on YouTube at 7:00 p.m.

Public Safety Center Construction Update – December 2019

Posted on December 6, 2019


Progress photo – view from City Hall

Construction of the Public Safety Center continues to move forward despite the weather conditions. In fact, the rainfall gave the contractor’s team the opportunity to test the building’s waterproofing. The facility’s basement is completely built, and its walls are painted. Additionally, rollup doors have been installed. Currently, the first-floor is being painted. The exterior stucco on Via Sessi and some of the south elevation is pretty much complete. The brick veneer will be delivered next week for the contractor to start installation. More information

Close window