Please note the time change of San Rafael Regular City Council Meetings to commence at 6:00 p.m. 

Fire Stations 54 & 55 project update

Posted on July 4, 2022


.

Contact:         A. Fabiola Guillen, Sr. Project Manager – Public Works

Construction continues at the two fire stations.

At Fire Station 54, Wickman Development and Construction, construction is well underway with wall framing and the concrete placement of the elevator tower.  The work was successfully completed last Thursday.  This is a critical milestone that will allow other important work to occur such as the roofing material installation.  Once the roof is complete, the drywall and interior finishes can begin.

The contractor is making incredible progress at Fire Station 55.  After the discovery and removal of the underground fuel tank at Fire Station 55, the crews have been able to start the foundation for the generator that will be located where the underground tank was found.  Wickman’s subcontractors are installing wall framing, rough electrical, mechanical, and plumbing.  The door frames and windows are also being installed along with other miscellaneous site activities.

.
Fire Station 54 – Wall framing
.
Fire Station 55 – Foundation prep for generator pad and footings
.
Fire Station 55 – New building wood framing & electrical rough in
Close window