Project Progress
During the month of November, Alten Construction substantially completed all excavation activity for the new storm drain. Form work and concrete pours for all manholes and inlets continued throughout the month. Temporary storm drain bypass measures were maintained and a secondary bypass pump was removed due to decreased rainfall. The review and processing of submittals and Request for Information (RFI’s) continued at high volume/pace. November construction progress on the storm drain bypass will allow normal building pad prep to begin in December.
PROJECT TEAM:
Owner: City of San Rafael
Project/Construction Manager: Kitchell, Sacramento, CA
Architect: Mary McGrath Architects, Oakland, CA
Contractor – Alten Construction, Inc.
Back to Monthly Updates