2025 Public Service Award Nominations are open! 

 

FAQ Tag: Fourth Street

How will traffic be impacted during construction?

To minimize impacts to the community, City staff will coordinate with the project contractor to ensure bicyclist and pedestrian access, and traffic flow are considered during the development of the project construction schedule and traffic control plan.

When will the proposed traffic signal be constructed?

Design and construction of the proposed traffic signal for West Crescent and Fourth Street intersection is/will be a part of the Second St and Fourth St intersection project. Construction of the traffic signal at West Crescent Dr and Fourth St is anticipated to begin in 2025.

What is the current project status?

The project team has prepared 65% construction documents and continues to collaborate with project stakeholders in the development of the 95% construction documents. The team anticipates design completion and the bidding of the project in 2025.