Category: Pickleweed Field and Park
Construction work continues on the City’s Pickleweed Park Enhancement project that began in September 2024. In preparation for the installation of the all-weather turf, the contractor has removed the existing grass field and is preparing the final grading. Most of the demolition work has been completed as well as minor concrete work and the installation … Continued
This week, Bayside Stripe & Seal, Inc. was awarded the Canal Parking Striping Project. Scheduled to commence shortly, the project will involve implementing new striping in the Canal neighborhood, including street parking spaces and red and yellow curb areas. Aimed at alleviating limited parking and enhancing neighborhood traffic safety, this initiative addresses critical concerns within … Continued
Toward the end of the month, the Parks Division knocked out a comprehensive clean-up around the entire front of the Al Boro Community Center in Pickleweed Park. Here you can see the crew focused on trimming the roses along the front and knocking down the weeds.
Bid advertised: January 25, 2024 Submission deadline: February 20, 2024 The City recently advertised our Canal Striping Project on BidExpress. The project objective is to remove conflicting striping and install new striping, including red curb, yellow curb, and parking Ts and Ls on various streets in the Canal neighborhood. This project is still being advertised … Continued
Notice of permit application: Pickleweed Park Public Notice
Design work continues for the Pickleweed Park Enhancement Project. City staff have worked alongside various design consultants and interdepartmental teams to carefully plan a project that will genuinely benefit the community while staying within the available grant budget. 90% of the plans are anticipated to be completed this December. If everything continues as scheduled, construction … Continued