Project Description
The AC Marriott Hotel project was approved on April 23, 2019. City approvals authorized demolition of an existing 10,600 square foot office building, associated tree removal (on-site and within the right-of-way), and construction of a 54 feet tall, 140-room hotel building and associated parking and landscape improvements. The project also includes a rooftop lounge area. The following is the project’s expected schedule:
TASK | EXPECTED COMPLETION DATE |
Completion of exterior work | December 2021 (a slight delay may occur due to the recent rains) |
Completion of interior work | June 2022 |
Approximate date the hotel will be operational | Feb/March 2023 |
Approximate date the rooftop lounge will be operational | Feb/March 2023 |