Project DescriptionThe AC Marriot Hotel project was approved on April 23, 2019. City approvals authorized demolition of an existing 10,600 square foot office building, associated tree removal (on-site and within the right-of-way), and construction of a 54 feet tall, 140-room hotel building and associated parking and landscape improvements. The project also includes a rooftop lounge area. The following is the project’s expected schedule
TASK EXPECTED START EXPECTED COMPLETION STATUS DEMOLITION November 2019 November 2019 Under Construction SHORING November 2019 December 2019 FOUNDATION/PODIUM January 2020 August 2020 BUILDING August 2020 Fall 2021
The AC Marriot Hotel project was approved on April 23, 2019. City approvals authorized demolition of an existing 10,600 square foot office building, associated tree removal (on-site and within the right-of-way), and construction of a 54 feet tall, 140-room hotel building and associated parking and landscape improvements. The project also includes a rooftop lounge area. The following is the project’s expected schedule
TASK | EXPECTED START | EXPECTED COMPLETION | STATUS |
DEMOLITION | November 2019 | November 2019 | Under Construction |
SHORING | November 2019 | December 2019 | |
FOUNDATION/PODIUM | January 2020 | August 2020 | |
BUILDING | August 2020 | Fall 2021 |