3rd Street Sewer Repairs Project (Sanitation District)

Project Goals

Sewer main  repair and replace on 3rd Street between Miracle Mile and Grand Avenue.  Also, relocating and repairing sewer main pipes in the Miraflores Avenue and Miramar Avenue areas.

 

Budget

Construction $3,872,000

 

Overview

This project is a part of a much larger City Department of Public Works (DPW) project on 3rd Street between Miracle Mile and Grand Avenue.  Along with all the proposed improvements that DPW is doing, SRSD will be having several sewer main sections repaired and replaced.

Also, as a part of this project SRSD will be relocating and repairing sewer main pipes in the Miraflores Avenue and Miramar Avenue areas.

Timeline

Construction  March 14, 2022 - May 12, 2023

 

Project Contact

Tim Tran | Project Manager/Associate Civil Engineer
Tim.Tran@cityofsanrafael.org
415.451.2441