SMART Larkspur Extension Update September 7, 2018

Posted on September 7, 2018


Progress on the SMART Larkspur extension construction continues to move rapidly with the Francisco Blvd. West realignment and Phase-1 of the Multi-Use Path (from Rice Street to Andersen Drive). The Contractor has placed the aggregate base and is now installing curb & gutter on the north end.

dpw
Francisco Blvd. West and SMART Rail Realignment
Curb & Gutter

dpw
Francisco Blvd. West and SMART Rail Realignment
Curb & Gutter Framing.

Construction of the Multi Use Path-Phase 1 is going well. The pile driving contractor is now installing sheet piles and Stacy-Witbeck is starting to install the prefabricated bents on top of the concrete piles.

dpw
Multi-Use Path – Sheet Pile Driving.

dpw
Multi-Use Path – Bent Installation.

 