2020 Sewer Replacement Phase 2 – Weekly Update February 21th

Posted on February 21, 2023


Sewer Lateral Replacement on 1st St

Project Update – Week of 2/20

WR Forde completed sanitary sewer main replacement on Marin St from Clayton Ave to Ross St.

Sewer laterals on Marin from Clayton Ave to Ross St will be replaced and expected to be completed by February 24th.

From 2/20 – 3/10, WR Forde will be on Clayton Ave and Welch St for CCTV, potholing, then replacing sewer main on Clayton Ave.

The contractor will return to 1st St, E St, Frances St, and Marin St for final paving after completing sewer replacement works on Clayton Ave and Welch St.