2020 Sewer Replacement Phase 2 – Weekly Update April 26th

Posted on April 26, 2023


Road workers and excavator laying asphalt. San Rafael, 4/12/23 at 2:54pm

Project Update

Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Clayton St

The contractor will replace sewer main and sewer laterals on 1st St between B St and C St from April 28th to May 19th.

The contractor will replace sewer main and sewer laterals on 2nd St and East St from May 15th to May 29th.