Project Update

Replaced sewer main and sewer laterals and temporarily paved sewer laterals on Welch St

Replaced sewer main on Clayton St from Marin St to Welch St

The contractor will replace sewer main and sewer laterals on Clayton St from April 10th to April 21th.