West End Village Project

FOURTH STREET REHABILITATION/
WEST END VILLAGE PROJECT (#11056)

Project Location:
LOCATION MAP OF FOURTH STREET PROJECT

Contact: Department of Public Works (415) 485-3355

Limits of Work: Fourth Street from D St to Second St
 
Description of Work: Replace sidewalks on both sides of Fourth St. Grind & repave Fourth St,
 
install new trees, tree up-lighting and future twinkle lighting.

Construction dates: May, 2008 through Summer, 2009

Contractor:
The bid was awarded to Ghilotti Construction Co. Bid amount - $3,278,234

FourthStreetProjectBidSummary (pdf format: 44K)

Budget:$5,133,660

Funding sources: $5,133,660
   Regional & Local Measure A
   Traffic Mitigation Fees
   Gas Tax

 

Activities/Meetings:
None 

Sequence of  Operations:
There will be no on street parking in the active construction area.  On street parking will remain available in the blocks surrounding the work area.  Parking will also be available in the public parking lot located next to United Liquors.

The sidewalk removal will occur in two phases to allow maximum public access to the businesses and residences.  In the first phase, the contractor will sawcut the sidewalk approximately 4’ from the existing buildings and the sidewalk between the the sawcut line and the street will be demolished. Public access will continue on the four foot section.  The public will be protected from the demolition by a railing.

Once the area between the curb and the sawcut section is completed, the section nearest to the building will be demolished and removed.  During this phase, pedestrain traffic will be relocated to the parking lane in the street and adequate safety delineation provided.  The contractor will construct access bridges to each business or residence. 

Using this two phase system will limit the impact to businesses and residences.  It is anticipated that each construction stage will occur over eight weeks but the impact to the businesses will be limited to the time that the contractor is demolishing and replacing the sidewalk directly in front of the business access.

 Standard Stage Sequence:
1. Sawcut 3’-4’ from building (public use of 3’-4’ area)
2. Demolish portion of sidewalk and curb and gutter
3. Construct joint trench
4. Grade form and pour curb and gutter
5. Place irrigation and light foundations
6. Adjust utilities to grade
7. Switch public to streetside
8. Demolish 3’-4’ concrete sidewalk
9. Grade form and pour sidewalk

The project plans have broken down the project into stages.

              Approximate Dates* 
Stage 1 (North): Far West to H St.              May 5 – June 25  
Stage 2 (North): H St. to F St.                    July 10 – September 3
Stage 3 (North): F St. to E St.                    May 12 – July 15
Stage 4 (North): E St. to D St.                    July 23 – September 5
Stage 5 (South): E St to D St.                    June 20 – July 28
Stage 6 (South): F St. to E St.                   August 28 – October 31
Stage 7 (South): Ida St to F St.                  October 14 – December 10
State 8 (South): Far West to Ida St.            August 26 – November 4
Trees and Landscaping                              January 2 – February 3, 2009
Paving (Night):                                          January 8  - January 13, 2009
Punchlist                                                  End February 5, 2009

* These dates are approximate and subject to change and do not fully reflect the Early Finish Questionnaire.

“Hopskotch” plan: There will be two stages open at any one time. There will be one stage not worked on between two worked on stages at any given time.
1. Stage 1 to 5 to 4 to 6
2. Stage 3 to 2 to 8 to 7

Work This and Next Week:
-Complete tree removal
-Stage 1 - Temporary overhead lighting
-Stage 1 – Continue sidewalk and curb and gutter removal
-Stage 1 - Start joint trench and pouring curb and gutter

Work Next Few Weeks:
-Work on the Shaver St. and Fourth St. corner storm drain pipe should be completed on May 16. Contractor may work nights.
-Stage 1 – Complete concrete work the week of June 2
-Stage 3 - Work will start the week of May 12 and work toward the East
Date Last Updated: 2008-05-09