Fourth Street Rehabilitation Project

FOURTH STREET REHABILITATION/
WEST END VILLAGE PROJECT (#11056) 
 Back to Current Projects

Project Location:
LOCATION MAP OF FOURTH STREET PROJECT

Contact: Department of Public Works (415) 485-3355

Limits of Work: Fourth Street from D St to Second St
 
Description of Work: Replace sidewalks on both sides of Fourth St. Grind & repave Fourth St,
 
install new trees, tree up-lighting and future twinkle lighting.

Construction dates: May, 2008 through Winter, 2009

Contractor:
The bid was awarded to Ghilotti Construction Co. Bid amount - $3,278,234

FourthStreetProjectBidSummary (pdf format: 44K)

Budget:$5,133,660

Funding sources: $5,133,660
   Regional & Local Measure A
   Traffic Mitigation Fees
   Gas Tax

 

Activities/Meetings:
None 

 

Percent Complete: 35%

Sequence of  Operations:
There will be no on street parking in the active construction area.  On street parking will remain available in the blocks surrounding the work area.  Parking will also be available in the public parking lot located next to United Liquors.

The sidewalk removal will occur in two phases to allow maximum public access to the businesses and residences.  In the first phase, the contractor will sawcut the sidewalk approximately 4’ from the existing buildings and the sidewalk between the the sawcut line and the street will be demolished. Public access will continue on the four foot section.  The public will be protected from the demolition by a railing.

Once the area between the curb and the sawcut section is completed, the section nearest to the building will be demolished and removed.  During this phase, pedestrain traffic will be relocated to the parking lane in the street and adequate safety delineation provided.  The contractor will construct access bridges to each business or residence. 

Using this two phase system will limit the impact to businesses and residences.  It is anticipated that each construction stage will occur over eight weeks but the impact to the businesses will be limited to the time that the contractor is demolishing and replacing the sidewalk directly in front of the business access.

 Standard Stage Sequence:
1. Sawcut 3’-4’ from building (public use of 3’-4’ area)
2. Demolish portion of sidewalk and curb and gutter
3. Construct joint trench
4. Grade form and pour curb and gutter
5. Place irrigation and light foundations
6. Adjust utilities to grade
7. Switch public to streetside
8. Demolish 3’-4’ concrete sidewalk
9. Grade form and pour sidewalk

 Fourth Street Staging Map
STAGING LOCATIONS & SCHEDULING

                                                                     Approximate Dates*    


Stage 1 (North): Far West to H St.                May 5 – June 13  
Stage 2 (North): H St. to F St.                      June 19 – July 23
Stage 3 (North): F St. to E St.                      May 12 – June 25**
Stage 4 (North): E St. to D St.                      July 23 – Mid-August
Stage 5 (South): E St to D St.                       Mid-Aug – Mid-September
Stage 6 (South): F St. to E St.                      July 11 – Mid-Aug
Stage 7 (South): Ida St to F St.                     Mid-Aug – Mid-September
State 8 (South): Far West to Ida St.               June 12 – July 16
Trees and Landscaping                                 Early November – Late November
Paving (Night):                                             Mid-November
Punchlist                                                     Early January, 2009

* These dates are approximate and subject to change.
“* Portions of the sidewalk will be removed and replaced due to out of specification finishing. This work is anticipated
to occur on July 12.

Hopskotch plan: There will be two stages open at any one time. There will be one stage not worked on between two active stages at any given time.

   Stage 1 to 8 to 6 to 7 
   Stage 3 to 2 to 4 to 5

Work Hours:
The Contractor will start work at approximately 7am. However, on concrete pour days when the Contractor is placing concrete, the start time will be 6am. The earlier time allows the Contractor to complete their work by the time that merchants are opening for business.

Next major concrete pours:
-Stage 2 July 23
-Stage 4 Aug 1, 11, 12
-Stage 6 July 28, Aug 11-13

Work This and Next Week:
-Stage 2 – Complete work by July 23
-Stage 4 – Start sidewalk work
-Stage 6 – Continue sidewalk work
-Stage 8 – Complete sidewalk work by July 16
-Work on Shaver St and Fourth St corner storm drain pipe

Work Next Few Weeks:
-Stage 5 start in mid-Aug
-Stage 7 start in mid-Aug

Date Last Updated: 07-21-08

 